PG Acrylic
APPLICATION NOTE

A tunnel is not a flat panel.
The geometry changes everything.

Underwater tunnel acrylic panels — curved PMMA geometry, segment joints, installation sequence, and thickness range 150–400mm.

An underwater tunnel looks like a series of panels curved into an arch. It is actually a system — where panel geometry, joint design, installation sequence, and civil structure must all be resolved together before any fabrication begins. This note explains what that means in practice.

Cast & formed PMMA 150–400mm typical Curved geometry Segment joint design critical Sequence governs installation
FROM THE FIELD

Tunnel joints need different preparation — and it matters before the panel goes in

Jointing between tunnel panels is not the same as jointing on a pool wall or a fish tank.

Before the sealant goes in, the acrylic surface needs specific preparation — the process is different from a standard installation, and if it isn't done correctly, the joint won't perform under sustained water pressure. This is one of those steps that looks minor in a specification document and becomes a site problem if it's skipped or done out of sequence.

We walk through the joint preparation requirements before fabrication is confirmed, not after the panels arrive on site.

NOT A FLAT PANEL

What changes when you go from a flat panel to a curved tunnel segment.

Flat panels have two structural inputs and one perimeter interface to design. Tunnel segments have four structural inputs, a joint at every edge, and an installation sequence that is itself a structural constraint.

Flat panel

Two inputs, one interface

Thickness determined by span and depth. One perimeter interface to design. Installation is sequential and largely reversible if something is wrong.

Tunnel segment

Four inputs, joints everywhere

Thickness governed by radius, depth, arc span, and safety factor. A joint at every panel edge. Installation sequence is a structural constraint — not a logistics choice.

The critical difference

Sequence determines sealing

In a flat panel installation, sequence is about access. In a tunnel, sequence determines whether each joint can be physically reached to be sealed. Get it wrong and panels must be removed.

Completed acrylic underwater tunnel interior — curved PMMA segment panels forming full arch enclosure, joint rings visible at crown and haunch, fish and coral visible through panels, walk-through aquarium tunnel installation
Completed walk-through tunnel — segment joint rings visible at crown and haunch; panel arc width and ring spacing determined before fabrication
GEOMETRY PARAMETERS

The four inputs that govern tunnel panel thickness and forming geometry.

ParameterWhat it meansWhy it matters
Internal radiusInternal radius of the tunnel cross-sectionGoverns curvature of each segment — smaller radius limits maximum panel arc width and increases forming complexity
Water depth to crownDepth from water surface to top of the tunnel archCrown carries the highest pressure load in a fully submerged tunnel — governs the upper segment thickness
Arc span between jointsArc length of each segment between joint centre linesShorter segments reduce bending demand but increase joint count — each joint is a potential leak point
Safety factorDesign margin on characteristic PMMA tensile strengthPublic walk-through tunnels typically require 3.5–4.5 — higher than residential pool wall applications
ApplicationInternal radiusDepth to crownIndicative thickness
Small tunnel1.5–2.0m3–5m150–220mm
Standard aquarium tunnel2.0–3.0m4–7m200–280mm
Large oceanarium tunnel3.0–4.5m6–10m250–360mm
Mega tunnel4.5m+8–14m300–400mm

Indicative only. Curved geometry affects structural behaviour — final thickness requires project-specific review for each tunnel configuration.

Large-radius acrylic underwater tunnel completed — wide-span curved PMMA panels with visitors for scale, showing internal radius and arch geometry, aquarium walk-through tunnel
JOINT DESIGN

Every joint is a sealing problem. Resolve it in the drawing, not on site.

In a flat panel installation, there is typically one perimeter seal to design. In a tunnel, there is a joint at every segment edge — and at the base corner, where curved side panels meet the flat floor panel, the geometry is the most demanding on the whole project.

Rebate geometry at each joint

  • Rebate depth and width at each joint line
  • Panel edge clearance and spring-back allowance from forming
  • Rebate in the civil ring — must be cast to acrylic panel tolerance

Compression seal continuity

  • Seal type and compression across the arc
  • Corner seal continuity at panel transitions — crown, haunch, and base
  • Access for seal replacement after flooding — not guaranteed once assembled

Base corner — the hardest joint

  • Where curved side panels meet the flat floor — geometry changes at this transition
  • Requires a custom transition detail — not handleable with a standard rebate and seal
  • Most common source of tunnel leaks when not designed explicitly in advance
INSTALLATION SEQUENCE

The sequence is a structural decision — not a site logistics decision.

Each panel must be placed in a specific order so that the joint to the previous panel can be sealed before the next panel closes access. This sequence must be confirmed before fabrication — not worked out by the installer on site.

Correct approach

Sequence confirmed in the fabrication package

Installation sequence is documented and approved before panels are fabricated. Panel numbering, delivery order, and joint sealing access are all confirmed. The installer follows a defined sequence — no improvisation required on site.

What happens otherwise

Sequence resolved on site

Installer places panels in a logical order that is not the sealing order. A joint becomes inaccessible before it is sealed. The blocking panel must be removed — the sealant joint is damaged in removal, or the panel is. Rework at installation stage is the most expensive rework in a tunnel project.

Small-radius acrylic underwater tunnel completed — tight curved PMMA segments with narrow arc span, base corner transition where curved side panels meet flat floor visible, compact walk-through aquarium tunnel
Small-radius tunnel — tighter curvature increases segment count and forming tolerance demands; base corner detail must be resolved before fabrication
CIVIL COORDINATION

Three parties who must be in the same design conversation before fabrication begins.

Acrylic fabricator

Provides panel dimensions, forming radius tolerance, edge rebate requirements, and installation sequence. Must know structural ring geometry before machining begins — the panels are machined to fit the ring, not the ring built to fit whatever arrives.

Civil / structural engineer

Designs the bearing ring that supports the panels. Ring geometry and surface tolerance must accommodate acrylic panel edges and rebate. Ring construction precedes panel installation — errors in the ring cannot be corrected after it is cast.

Installation contractor

Executes the confirmed installation sequence. Must have panel delivery schedule, lifting plan, and joint sealing access confirmed before work begins. Site improvisation in tunnel installation is a project risk, not a problem-solving opportunity.

The coordination risk: All three parties need design information from each other before they can finalise their own scope. The earliest this three-way alignment happens, the fewer constraints carry through to site. The latest it can happen is before civil ring construction begins — not before installation begins.
FREQUENTLY ASKED

Underwater tunnel — questions that come up on every project

How thick are acrylic underwater tunnel panels?

Typically 150–400mm depending on tunnel radius, water depth above crown, arc span between joints, and safety factor. Curved geometry provides structural efficiency — reducing required thickness compared to an equivalent flat panel under the same pressure. Final thickness requires project-specific calculation for each tunnel configuration.

Why is an underwater tunnel more complex than a flat viewing panel?

Each panel must be placed so that the joint between it and the previous panel can be sealed before the next panel blocks access to that joint. If the sequence is wrong, a joint becomes inaccessible — and the blocking panel must be removed to complete sealing. Removal risks damage to the sealant or the panel. The sequence must be confirmed before fabrication, not worked out on site.

What is the most critical step in underwater tunnel installation?

Confirming the installation sequence before fabrication begins. Each panel must be placed in a specific order so that the joint to the previous panel can be sealed before the next panel closes access. If a joint becomes inaccessible, the blocking panel must be removed to complete sealing — removal risks damage to the sealant or the panel itself. Sequence is a structural decision, not a site logistics choice.

How many segments does an acrylic underwater tunnel typically have?

A typical walk-through tunnel uses 6–12 curved segments per ring cross-section plus a flat base panel. Segment count depends on tunnel diameter, maximum panel arc width from the forming process, and access requirements for joint sealing during installation.

When is a tunnel project ready for technical evaluation?

When tunnel internal radius, water depth to crown, indicative segment count or arc span, and structural ring material are confirmed. A cross-section drawing — even at sketch level — is the single most useful input for technical evaluation of a tunnel project.

INSTALLED PROJECTS

Three engineering problems. Three completed tunnels.

Each tunnel configuration presents a different geometry challenge. These completed projects illustrate how segment count, radius, and joint design vary across tunnel types — and why each requires a separate engineering resolution before fabrication begins.

PG Acrylic has delivered walk-through acrylic tunnel segments up to 25.8 m — including the Acuario Nautilus tunnel in Peru (70 mm curved cast-PMMA panels, 800 mm water depth). For integrator Forma Fabrica (Gdańsk, Poland), PG supplied a 20.4 m tunnel build in 100 mm cast PMMA. A 6.5 m tunnel section was delivered for an aquarium project in India.

Read the 25.8m Nautilus tunnel project review →

Completed acrylic underwater tunnel showing curved PMMA segment joints — ring frame visible at crown and haunch, full enclosure walk-through tunnel with fish above, aquarium installation
Segment joints

Full-enclosure walk-through tunnel — joint ring spacing as the structural variable

A fully enclosed tunnel has a joint at every segment edge around the entire cross-section. Spacing between joint rings determines arc span — and arc span is one of the four inputs that governs panel thickness. Closer rings reduce bending demand but multiply the number of joints that must be sealed. The ring spacing decision is made before fabrication, not on site.

Full enclosure Ring joint design Arc span critical
Large-span acrylic underwater tunnel completed — wide internal radius walk-through tunnel with visitors, curved PMMA panels spanning full arch, natural light aquarium installation
Large radius

Large-radius tunnel — panel arc width and forming geometry at scale

A larger internal radius increases the arc width of each segment and requires a larger forming radius in fabrication. Maximum panel arc width is constrained by the casting and forming process — not by the project specification. For large-radius tunnels, segment count per ring cross-section is determined by this fabrication limit, not by the designer's preference. The forming geometry must be confirmed before the panel schedule is drawn up.

Large radius Forming geometry Arc width limit
Small-radius acrylic underwater tunnel completed — tight curved PMMA segments with narrow arc span, compact walk-through tunnel with fish and coral, aquarium installation
Small radius

Small-radius tunnel — tight curvature, forming precision, and base corner geometry

A smaller internal radius reduces the maximum arc width achievable per panel and increases the number of segments required around the cross-section. Tighter curvature also increases forming complexity and tolerance demands — spring-back behaviour at the panel edge affects rebate fit at every joint. The base corner, where curved side panels meet the flat floor, is where geometry is most demanding regardless of tunnel radius — and it requires a custom transition detail that is not resolvable with a standard seal.

Small radius Forming tolerance Base corner detail

Which configuration applies to your project? Internal radius, water depth to crown, and indicative tunnel length are the three inputs that determine which geometry constraints apply — and what needs to be resolved before fabrication can begin.

View all installed projects →
CERTIFICATIONS & TEST REPORTS

Material and quality documentation for tunnel-grade PMMA.

Tunnel projects involve multiple engineering parties. The following test reports and certificates are available for download to support your procurement and review process.

🏅

TÜV AUSTRIA SASO

Download certificate ↓
🔬

SGS Material Test

Download report ↓
📐

ASTM Test Report

Download report ↓

Bureau Veritas Inspection

Download report ↓
View all certifications →
OTHER APPLICATION NOTES

Related notes

Application note

Pool Viewing Wall

The engineering discipline behind the feature wall — span, interface, and what the design drawings need to show.

Read note →
Application note

Aquarium Viewing Panel

Most aquarium windows don't fail at thickness. They fail at how the panel sits in the frame.

Read note →
Application note

Oceanarium Panel

At this scale, the review package is as important as the panel itself.

Read note →
Application note

Thick PMMA Panel

Water depth is the load. Span is what breaks the panel. The methodology that applies to every application type.

Read note →
Coral & reef supply

Artificial Coral & Reef Supply

Custom artificial coral and reef structures for aquarium and marine attraction projects — colour-stable, fish-safe, coordinated with panel installation schedule.

Coral & Reef Supply →
Tunnel radius confirmed? That is when evaluation can begin. If internal radius, water depth to crown, and structural ring design intent are available, submit for project-specific evaluation. A cross-section drawing is the most useful input — include it even at sketch stage.
Submit requirements
TYPICAL SPECIFICATION

Thickness range and what we need from you.

Typical thickness range

150 – 400mm

One-time cast PMMA curved segments. Radius, tunnel length, and crown-to-waterline distance all affect thickness and forming geometry.

One-time castCurved PMMAOutdoor gradeUV resistantPolished edge

What to send us

Tunnel panels require three inputs that flat panels don't need: radius, total length, and the distance from tunnel crown to water surface. Without these, segment geometry and thickness cannot be calculated.

  • Tunnel internal radius
  • Total tunnel length
  • Distance from tunnel crown to water surface
  • Segment joint type and spacing
  • Civil structure drawings if available
NEXT STEP

Have a underwater tunnel project?

Send us your dimensions, water depth, and installation type. We'll confirm whether the thickness works, what's missing, and what needs to be resolved before fabrication.

Request Technical Review